CrewCanvas
Dana Ruiz
superintendent

HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen

Work packages

12 packages · scope, assignments and readiness

  • Foundations & footings

    03-100 · Concrete

    Complete
    Window
    Sep 8 – Sep 25
    Zone
    Building footprint
    Crew
    Summit Concrete Co. · Placement Crew 1
    100%
  • Structural steel — Levels 1–2

    05-110 · Structural steel

    Complete
    Window
    Sep 28 – Oct 9
    Zone
    Levels 1–2
    Crew
    Ironclad Steel Erectors · Raising Gang A
    Depends on
    Foundations & footings (FS)
    100%
  • Structural steel — Level 3 to roof

    05-120 · Structural steel

    Approved for work
    Window
    Oct 12 – Oct 23
    Zone
    Levels 3–Roof
    Crew
    Ironclad Steel Erectors · Raising Gang A
    Depends on
    Structural steel — Levels 1–2 (FS)
    45%trending Oct 27
  • Level 1 underground plumbing & rough-in

    22-300 · Plumbing

    Approved for work
    Window
    Oct 13 – Oct 21
    Zone
    Level 1 East
    Crew
    Delta Mechanical & Plumbing · Plumbing Crew 1
    Depends on
    Foundations & footings (FS)
    70%
  • Level 1 electrical rough-in

    26-310 · Electrical

    Approved for work
    Window
    Oct 20 – Oct 27
    Zone
    Level 1 West
    Crew
    Brightline Electric · Crew A
    0%
  • Fire sprinkler mains — Level 1

    21-330 · Fire sprinkler

    Approved for work
    Window
    Oct 20 – Oct 23
    Zone
    Level 1 East · exclusive
    Crew
    Apex Fire Protection · Sprinkler Crew
    0%
  • Level 2 slab-on-deck pour

    03-200 · Concrete

    Blocked
    Window
    Oct 22 – Oct 23
    Zone
    Level 2 · exclusive
    Crew
    Summit Concrete Co. · Placement Crew 1
    Depends on
    Structural steel — Levels 1–2 (FS)
    0%
  • Temporary power — Levels 2–3

    26-320 · Electrical

    Awaiting approval
    Window
    Oct 22 – Oct 23
    Zone
    Levels 2–3
    Crew
    Brightline Electric · Crew A
    0%
  • Curtain wall — north & east elevations

    08-400 · Curtain wall

    Verification outstanding
    Window
    Oct 26 – Nov 13
    Zone
    North & east elevations
    Crew
    Clearview Glazing · Install Crew
    Depends on
    Structural steel — Level 3 to roof (FS+2d)
    0%
  • Loading dock slab-on-grade

    03-210 · Concrete

    Awaiting approval
    Window
    Oct 28 – Oct 29
    Zone
    Loading dock
    Crew
    Summit Concrete Co. · Placement Crew 1
    Depends on
    Foundations & footings (FS)
    0%
  • Roofing — insulation & membrane

    07-500 · Roofing

    Verification outstanding
    Window
    Oct 29 – Nov 10
    Zone
    Roof
    Crew
    Ridgeline Roofing · Roofing Crew
    Depends on
    Structural steel — Level 3 to roof (FS+3d)
    0%
  • Level 2 framing & MEP rough-in

    09-600 · Multi-trade

    Verification outstanding
    Window
    Nov 2 – Nov 20
    Zone
    Level 2
    Crew
    Delta Mechanical & Plumbing · Plumbing Crew 1
    Depends on
    Level 2 slab-on-deck pour (FS+3d)
    0%

Dependency network

Finish-to-start links with lag and rationale

  • Foundations & footingsFS →Structural steel — Levels 1–2
  • Structural steel — Levels 1–2FS →Structural steel — Level 3 to roof
  • Structural steel — Levels 1–2FS →Level 2 slab-on-deck pour

    Deck pour requires accepted L1–L2 steel

  • Foundations & footingsFS →Level 1 underground plumbing & rough-in
  • Foundations & footingsFS →Loading dock slab-on-grade
  • Structural steel — Level 3 to roofFS+2d →Curtain wall — north & east elevations

    Survey of embed plates after topping out

  • Structural steel — Level 3 to roofFS+3d →Roofing — insulation & membrane

    Roof deck acceptance

  • Level 2 slab-on-deck pourFS+3d →Level 2 framing & MEP rough-in

    Slab cure before loading