HPM-26 · Harbor Point Health Partners
Harbor Point Medical Pavilion
Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf
Work packages
12 packages · scope, assignments and readiness
- Complete
Foundations & footings
03-100 · Concrete
- Window
- Sep 8 – Sep 25
- Zone
- Building footprint
- Crew
- Summit Concrete Co. · Placement Crew 1
100% - Complete
Structural steel — Levels 1–2
05-110 · Structural steel
- Window
- Sep 28 – Oct 9
- Zone
- Levels 1–2
- Crew
- Ironclad Steel Erectors · Raising Gang A
- Depends on
- Foundations & footings (FS)
100% - Approved for work
Structural steel — Level 3 to roof
05-120 · Structural steel
- Window
- Oct 12 – Oct 23
- Zone
- Levels 3–Roof
- Crew
- Ironclad Steel Erectors · Raising Gang A
- Depends on
- Structural steel — Levels 1–2 (FS)
45%trending Oct 27 - Approved for work
Level 1 underground plumbing & rough-in
22-300 · Plumbing
- Window
- Oct 13 – Oct 21
- Zone
- Level 1 East
- Crew
- Delta Mechanical & Plumbing · Plumbing Crew 1
- Depends on
- Foundations & footings (FS)
70% - Approved for work
Level 1 electrical rough-in
26-310 · Electrical
- Window
- Oct 20 – Oct 27
- Zone
- Level 1 West
- Crew
- Brightline Electric · Crew A
0% - Approved for work
Fire sprinkler mains — Level 1
21-330 · Fire sprinkler
- Window
- Oct 20 – Oct 23
- Zone
- Level 1 East · exclusive
- Crew
- Apex Fire Protection · Sprinkler Crew
0% - Blocked
Level 2 slab-on-deck pour
03-200 · Concrete
- Window
- Oct 22 – Oct 23
- Zone
- Level 2 · exclusive
- Crew
- Summit Concrete Co. · Placement Crew 1
- Depends on
- Structural steel — Levels 1–2 (FS)
0% - Awaiting approval
Temporary power — Levels 2–3
26-320 · Electrical
- Window
- Oct 22 – Oct 23
- Zone
- Levels 2–3
- Crew
- Brightline Electric · Crew A
0% - Verification outstanding
Curtain wall — north & east elevations
08-400 · Curtain wall
- Window
- Oct 26 – Nov 13
- Zone
- North & east elevations
- Crew
- Clearview Glazing · Install Crew
- Depends on
- Structural steel — Level 3 to roof (FS+2d)
0% - Awaiting approval
Loading dock slab-on-grade
03-210 · Concrete
- Window
- Oct 28 – Oct 29
- Zone
- Loading dock
- Crew
- Summit Concrete Co. · Placement Crew 1
- Depends on
- Foundations & footings (FS)
0% - Verification outstanding
Roofing — insulation & membrane
07-500 · Roofing
- Window
- Oct 29 – Nov 10
- Zone
- Roof
- Crew
- Ridgeline Roofing · Roofing Crew
- Depends on
- Structural steel — Level 3 to roof (FS+3d)
0% - Verification outstanding
Level 2 framing & MEP rough-in
09-600 · Multi-trade
- Window
- Nov 2 – Nov 20
- Zone
- Level 2
- Crew
- Delta Mechanical & Plumbing · Plumbing Crew 1
- Depends on
- Level 2 slab-on-deck pour (FS+3d)
0%
| Package | Zone | Subcontractor · crew | Window | Progress | Depends on | Readiness |
|---|---|---|---|---|---|---|
Foundations & footings 03-100 · Concrete | Building footprint | Summit Concrete Co. Placement Crew 1 | Sep 8 – Sep 25 | 100% | — | Complete |
Structural steel — Levels 1–2 05-110 · Structural steel · 90T mobile crane | Levels 1–2 | Ironclad Steel Erectors Raising Gang A | Sep 28 – Oct 9 | 100% | 03-100 FS · done | Complete |
Structural steel — Level 3 to roof 05-120 · Structural steel · 90T mobile crane | Levels 3–Roof | Ironclad Steel Erectors Raising Gang A | Oct 12 – Oct 23 | 45% plan 58% · trending Oct 27 | 05-110 FS · done | Approved for work |
Level 1 underground plumbing & rough-in 22-300 · Plumbing | Level 1 East | Delta Mechanical & Plumbing Plumbing Crew 1 | Oct 13 – Oct 21 | 70% plan 67% | 03-100 FS · done | Approved for work |
Level 1 electrical rough-in 26-310 · Electrical · Scissor lift | Level 1 West | Brightline Electric Crew A | Oct 20 – Oct 27 | 0% | — | Approved for work |
Fire sprinkler mains — Level 1 21-330 · Fire sprinkler · Scissor lift | Level 1 Eastexclusive | Apex Fire Protection Sprinkler Crew | Oct 20 – Oct 23 | 0% | — | Approved for work |
Level 2 slab-on-deck pour 03-200 · Concrete · 42m concrete pump | Level 2exclusive | Summit Concrete Co. Placement Crew 1 | Oct 22 – Oct 23 | 0% | 05-110 FS · done | Blocked |
Temporary power — Levels 2–3 26-320 · Electrical | Levels 2–3 | Brightline Electric Crew A | Oct 22 – Oct 23 | 0% | — | Awaiting approval |
Curtain wall — north & east elevations 08-400 · Curtain wall · Glass vacuum lifter | North & east elevations | Clearview Glazing Install Crew | Oct 26 – Nov 13 | 0% | 05-120 FS+2d · earliest Oct 30 | Verification outstanding |
Loading dock slab-on-grade 03-210 · Concrete | Loading dock | Summit Concrete Co. Placement Crew 1 | Oct 28 – Oct 29 | 0% | 03-100 FS · done | Awaiting approval |
Roofing — insulation & membrane 07-500 · Roofing · 90T mobile crane | Roof | Ridgeline Roofing Roofing Crew | Oct 29 – Nov 10 | 0% | 05-120 FS+3d · earliest Oct 31 | Verification outstanding |
Level 2 framing & MEP rough-in 09-600 · Multi-trade | Level 2 | Delta Mechanical & Plumbing Plumbing Crew 1 | Nov 2 – Nov 20 | 0% | 03-200 FS+3d · earliest Oct 27 | Verification outstanding |
Dependency network
Finish-to-start links with lag and rationale
- Foundations & footingsFS →Structural steel — Levels 1–2
- Structural steel — Levels 1–2FS →Structural steel — Level 3 to roof
- Structural steel — Levels 1–2FS →Level 2 slab-on-deck pour
Deck pour requires accepted L1–L2 steel
- Foundations & footingsFS →Level 1 underground plumbing & rough-in
- Foundations & footingsFS →Loading dock slab-on-grade
- Structural steel — Level 3 to roofFS+2d →Curtain wall — north & east elevations
Survey of embed plates after topping out
- Structural steel — Level 3 to roofFS+3d →Roofing — insulation & membrane
Roof deck acceptance
- Level 2 slab-on-deck pourFS+3d →Level 2 framing & MEP rough-in
Slab cure before loading