HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen

Structural steel — Level 3 to roof

3 items · 2/2 required checklist items verified

Approved for work
Activity summary
  • roof-beams-a.jpg

    Roof beams grid A — crane pick

    Dana Ruiz · Oct 17, 1:10 PM

  • Progress note

    Steel L3–Roof daily progress

    Columns L3 set grids A–D. Roof beams started grid A. Erector reports bolt-up running ~2 days behind; one ironworker out Thu–Fri.

    Dana Ruiz · Oct 16, 4:45 PM

  • l3-perimeter-cable.jpg

    L3 perimeter cable installed — east side

    Owen Hale · Oct 9, 11:20 AM

Level 2 slab-on-deck pour

4 items · 5/6 required checklist items verified

Blocked
Activity summary
  • l2-edge-protection.jpg

    L2 leading-edge protection — north bay

    Owen Hale · Oct 17, 10:25 AM

  • Progress note

    Special inspection follow-up

    Called Keystone 10/16. Inspector tentatively Oct 20 AM; written report not yet issued.

    Marcus Chen · Oct 16, 3:30 PM

  • Checklist result

    MEP embed sign-off sheet — Level 2

    Delta, Brightline and Apex initialed all 38 sleeve and embed locations. 2 sleeves relocated at grid B/2 per RFI-041.

    Priya Natarajan · Oct 16, 3:00 PM

  • deck-sidelap-c4.jpg

    L2 deck side-lap fasteners — grid C/4

    Priya Natarajan · Oct 16, 2:05 PM

Loading dock slab-on-grade

1 item · 3/3 required checklist items verified

Awaiting approval
Activity summary

1 submission (0 photo, 1 checklist result, 0 note) from Priya Natarajan; latest “Loading dock subgrade compaction — 96% Proctor”. Checklist: 3 of 3 required items verified.

AIDeterministic summary (Bedrock off)
  • Checklist result

    Loading dock subgrade compaction — 96% Proctor

    Priya Natarajan · Oct 14, 1:00 PM

Level 1 underground plumbing & rough-in

2 items · 1/1 required checklist items verified

Approved for work
Activity summary
  • Progress note

    Plumbing L1 East status

    Underground complete. Above-ground rough-in 70%. Delta needs L1 East through Oct 21 for vent stacks.

    Dana Ruiz · Oct 16, 4:50 PM

  • l1-east-trench.jpg

    L1 East underground — trench before backfill

    Priya Natarajan · Oct 15, 12:00 PM

Submit evidence

Photos and PDFs upload directly to Amazon S3

Evidence documents work; it does not verify checklist items. Verification is recorded on the Readiness tab.