HPM-26 · Harbor Point Health Partners
Harbor Point Medical Pavilion
Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf
Structural steel — Level 3 to roof
3 items · 2/2 required checklist items verified
- roof-beams-a.jpg
Roof beams grid A — crane pick
Dana Ruiz · Oct 17, 1:10 PM
- Progress note
Steel L3–Roof daily progress
Columns L3 set grids A–D. Roof beams started grid A. Erector reports bolt-up running ~2 days behind; one ironworker out Thu–Fri.
Dana Ruiz · Oct 16, 4:45 PM
- l3-perimeter-cable.jpg
L3 perimeter cable installed — east side
Owen Hale · Oct 9, 11:20 AM
Level 2 slab-on-deck pour
4 items · 5/6 required checklist items verified
- l2-edge-protection.jpg
L2 leading-edge protection — north bay
Owen Hale · Oct 17, 10:25 AM
- Progress note
Special inspection follow-up
Called Keystone 10/16. Inspector tentatively Oct 20 AM; written report not yet issued.
Marcus Chen · Oct 16, 3:30 PM
- Checklist result
MEP embed sign-off sheet — Level 2
Delta, Brightline and Apex initialed all 38 sleeve and embed locations. 2 sleeves relocated at grid B/2 per RFI-041.
Priya Natarajan · Oct 16, 3:00 PM
- deck-sidelap-c4.jpg
L2 deck side-lap fasteners — grid C/4
Priya Natarajan · Oct 16, 2:05 PM
Loading dock slab-on-grade
1 item · 3/3 required checklist items verified
1 submission (0 photo, 1 checklist result, 0 note) from Priya Natarajan; latest “Loading dock subgrade compaction — 96% Proctor”. Checklist: 3 of 3 required items verified.
AIDeterministic summary (Bedrock off)- Checklist result
Loading dock subgrade compaction — 96% Proctor
Priya Natarajan · Oct 14, 1:00 PM
Level 1 underground plumbing & rough-in
2 items · 1/1 required checklist items verified
- Progress note
Plumbing L1 East status
Underground complete. Above-ground rough-in 70%. Delta needs L1 East through Oct 21 for vent stacks.
Dana Ruiz · Oct 16, 4:50 PM
- l1-east-trench.jpg
L1 East underground — trench before backfill
Priya Natarajan · Oct 15, 12:00 PM