HPM-26 · Harbor Point Health Partners
Harbor Point Medical Pavilion
Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf
Project timeline
Bars colored by readiness state · arrows are finish-to-start dependencies · dashed outline = projected finish at current production
Act now
Priority-1 corrective actions
- hold
Hold “Level 2 slab-on-deck pour” (Oct 22 – Oct 23). Do not release Summit Concrete Co. Placement Crew 1 or the 42m concrete pump until the outstanding item is verified.
Owner: Dana Ruiz (Superintendent) · Level 2 slab-on-deck pour · P1
- verify
Get “Special inspection of L2 steel connections (bolting & welds) — report received” from Keystone Testing & Inspection by Oct 21 and attach the report as evidence.
Owner: Marcus Chen (Project Manager) · Level 2 slab-on-deck pour · P1
- approve
Review the 2 verified checklist items for “Temporary power — Levels 2–3” and record a readiness decision before Oct 22.
Owner: Dana Ruiz (Superintendent) · Temporary power — Levels 2–3 · P1
Schedule conflicts
Next 21 days
- criticalMissing prerequisiteOct 22 – Oct 23
Level 2 slab-on-deck pour: 1 unverified required item
Level 2 slab-on-deck pour is scheduled Oct 22 – Oct 23 but these required checklist items are not verified: “Special inspection of L2 steel connections (bolting & welds) — report received” (pending, Keystone Testing & Inspection).
- highConflicting work windowOct 20 – Oct 21
Level 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap
Level 1 East is marked exclusive for Fire sprinkler mains — Level 1, but both packages are scheduled there Oct 20 – Oct 21.
- highCrew double-bookedOct 22 – Oct 23
Brightline Electric Crew A assigned to two packages Oct 22 – Oct 23
Brightline Electric Crew A is assigned to “Level 1 electrical rough-in” and “Temporary power — Levels 2–3” during Oct 22 – Oct 23.
- highCrew unavailableOct 26 – Oct 27
Clearview Glazing Install Crew unavailable Oct 26 – Oct 27
“Curtain wall — north & east elevations” needs Clearview Glazing Install Crew Oct 26 – Oct 27. Recorded availability: Manufacturer installer certification (off site).
Starting soon
- Approved for work
Level 1 electrical rough-in
Oct 20 · 3/3 required items verified
- Approved for work
Fire sprinkler mains — Level 1
Oct 20 · 2/2 required items verified
- Blocked
Level 2 slab-on-deck pour
Oct 22 · 5/6 required items verified
- Awaiting approval
Temporary power — Levels 2–3
Oct 22 · 2/2 required items verified
- Verification outstanding
Curtain wall — north & east elevations
Oct 26 · 1/3 required items verified
- Awaiting approval
Loading dock slab-on-grade
Oct 28 · 3/3 required items verified
Latest evidence
Roof beams grid A — crane pick
Structural steel — Level 3 to roof · Oct 17, 1:10 PM
L2 leading-edge protection — north bay
Level 2 slab-on-deck pour · Oct 17, 10:25 AM
Plumbing L1 East status
Level 1 underground plumbing & rough-in · Oct 16, 4:50 PM
Steel L3–Roof daily progress
Structural steel — Level 3 to roof · Oct 16, 4:45 PM
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.