CrewCanvas
Dana Ruiz
superintendent

HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen
Readiness health
40
100 = no blockers or conflicts
Blocked
1
Conflicts
7
Awaiting approval
2
Package progress
26%
12 work packages

Project timeline

Bars colored by readiness state · arrows are finish-to-start dependencies · dashed outline = projected finish at current production

Foundations & footings03-100
Structural steel — Levels 1–205-110
Structural steel — Level 3 to roof05-120
Level 1 underground plumbing & rough-in22-300
Level 1 electrical rough-in26-310
Fire sprinkler mains — Level 121-330
Level 2 slab-on-deck pour03-200
Temporary power — Levels 2–326-320
Curtain wall — north & east elevations08-400
Loading dock slab-on-grade03-210
Roofing — insulation & membrane07-500
Level 2 framing & MEP rough-in09-600
FSSOct 12MTWTFSSOct 19MTWTFSSOct 26MTWTFSSNov 2MTWTFSSNov 9MTWTFSSNov 16MTWTFSSNov 23MFoundations & footings · Sep 8–Sep 25 · 100%Structural steel — Levels 1–2 · Sep 28–Oct 9 · 100%Structural steel — Level 3 to roof · Oct 12–Oct 23 · 45% · projected finish Oct 27Level 1 underground plumbing & rough-in · Oct 13–Oct 21 · 70%Level 1 electrical rough-in · Oct 20–Oct 27 · 0%Fire sprinkler mains — Level 1 · Oct 20–Oct 23 · 0%Level 2 slab-on-deck pour · Oct 22–Oct 23 · 0%Temporary power — Levels 2–3 · Oct 22–Oct 23 · 0%Curtain wall — north & east elevations · Oct 26–Nov 13 · 0%Loading dock slab-on-grade · Oct 28–Oct 29 · 0%Roofing — insulation & membrane · Oct 29–Nov 10 · 0%Level 2 framing & MEP rough-in · Nov 2–Nov 20 · 0%TODAY

Act now

Priority-1 corrective actions

All actions →
  1. hold

    Hold “Level 2 slab-on-deck pour” (Oct 22 – Oct 23). Do not release Summit Concrete Co. Placement Crew 1 or the 42m concrete pump until the outstanding item is verified.

    Owner: Dana Ruiz (Superintendent) · Level 2 slab-on-deck pour · P1

  2. verify

    Get “Special inspection of L2 steel connections (bolting & welds) — report received” from Keystone Testing & Inspection by Oct 21 and attach the report as evidence.

    Owner: Marcus Chen (Project Manager) · Level 2 slab-on-deck pour · P1

  3. approve

    Review the 2 verified checklist items for “Temporary power — Levels 2–3” and record a readiness decision before Oct 22.

    Owner: Dana Ruiz (Superintendent) · Temporary power — Levels 2–3 · P1

Schedule conflicts

Next 21 days

Risk view →
  • criticalMissing prerequisiteOct 22 – Oct 23

    Level 2 slab-on-deck pour: 1 unverified required item

    Level 2 slab-on-deck pour is scheduled Oct 22 – Oct 23 but these required checklist items are not verified: “Special inspection of L2 steel connections (bolting & welds) — report received” (pending, Keystone Testing & Inspection).

  • highConflicting work windowOct 20 – Oct 21

    Level 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap

    Level 1 East is marked exclusive for Fire sprinkler mains — Level 1, but both packages are scheduled there Oct 20 – Oct 21.

  • highCrew double-bookedOct 22 – Oct 23

    Brightline Electric Crew A assigned to two packages Oct 22 – Oct 23

    Brightline Electric Crew A is assigned to “Level 1 electrical rough-in” and “Temporary power — Levels 2–3” during Oct 22 – Oct 23.

  • highCrew unavailableOct 26 – Oct 27

    Clearview Glazing Install Crew unavailable Oct 26 – Oct 27

    “Curtain wall — north & east elevations” needs Clearview Glazing Install Crew Oct 26 – Oct 27. Recorded availability: Manufacturer installer certification (off site).

Starting soon

  • Level 1 electrical rough-in

    Oct 20 · 3/3 required items verified

    Approved for work
  • Fire sprinkler mains — Level 1

    Oct 20 · 2/2 required items verified

    Approved for work
  • Level 2 slab-on-deck pour

    Oct 22 · 5/6 required items verified

    Blocked
  • Temporary power — Levels 2–3

    Oct 22 · 2/2 required items verified

    Awaiting approval
  • Curtain wall — north & east elevations

    Oct 26 · 1/3 required items verified

    Verification outstanding
  • Loading dock slab-on-grade

    Oct 28 · 3/3 required items verified

    Awaiting approval

Latest evidence

Evidence →
  • Roof beams grid A — crane pick

    Structural steel — Level 3 to roof · Oct 17, 1:10 PM

  • L2 leading-edge protection — north bay

    Level 2 slab-on-deck pour · Oct 17, 10:25 AM

  • Plumbing L1 East status

    Level 1 underground plumbing & rough-in · Oct 16, 4:50 PM

  • Steel L3–Roof daily progress

    Structural steel — Level 3 to roof · Oct 16, 4:45 PM

Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.