Northline Builders · Portfolio
Project portfolio
As of Monday, October 19
Harbor Point Medical Pavilion
Bayview, WA · $28.4M
Healthcare · 4-story steel frame · 62,000 sf
- Blocked
- 1
- Conflicts
- 7
- Packages
- 2/12
Next: Level 1 electrical rough-in · Oct 20Approved for work
Northgate Logistics Center — Tenant Fit-out
Kent Valley, WA · $4.1M
Industrial · Interior fit-out · 18,500 sf office
- Blocked
- 0
- Conflicts
- 0
- Packages
- 0/3
Next: Office electrical rough-in · Oct 26Verification outstanding
Cedar Row Townhomes — Phase 2
Maple Hollow, WA · $9.7M
Multifamily · 24 wood-frame units
- Blocked
- 0
- Conflicts
- 0
- Packages
- 0/2
Next: Site utilities — sanitary & storm · Nov 2Verification outstanding
Highest-risk upcoming activities
Ranked across the portfolio by unresolved dependencies, conflicts and time to start
- Level 2 slab-on-deck pourcritical70
HPM-26 · Oct 22 – Oct 23
BlockedBlocked: 1 required item(s) unverified — Special inspection of L2 steel connections (bolting & welds) — report received.
- Curtain wall — north & east elevationshigh63
HPM-26 · Oct 26 – Nov 13
Verification outstanding2 required item(s) still to verify (next due Oct 23).
- Temporary power — Levels 2–3medium43
HPM-26 · Oct 22 – Oct 23
Awaiting approvalChecklist verified, but no human readiness approval is recorded.
- Structural steel — Level 3 to roofmedium35
HPM-26 · Oct 12 – Oct 23
Approved for workIronclad Steel Erectors Raising Gang A at reduced capacity Oct 22 – Oct 23.
- Level 1 underground plumbing & rough-inmedium35
HPM-26 · Oct 13 – Oct 21
Approved for workLevel 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap.
- Level 1 electrical rough-inmedium35
HPM-26 · Oct 20 – Oct 27
Approved for workBrightline Electric Crew A assigned to two packages Oct 22 – Oct 23.
- Fire sprinkler mains — Level 1medium35
HPM-26 · Oct 20 – Oct 23
Approved for workLevel 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap.
- Level 2 framing & MEP rough-inmedium30
HPM-26 · Nov 2 – Nov 20
Verification outstanding1 required item(s) still to verify (next due Oct 30).
| Activity | Window | Readiness | Risk | Top reason |
|---|---|---|---|---|
| Level 2 slab-on-deck pour HPM-26 · 03-200 | Oct 22 – Oct 23 | Blocked | critical 70 | Blocked: 1 required item(s) unverified — Special inspection of L2 steel connections (bolting & welds) — report received. |
| Curtain wall — north & east elevations HPM-26 · 08-400 | Oct 26 – Nov 13 | Verification outstanding | high 63 | 2 required item(s) still to verify (next due Oct 23). |
| Temporary power — Levels 2–3 HPM-26 · 26-320 | Oct 22 – Oct 23 | Awaiting approval | medium 43 | Checklist verified, but no human readiness approval is recorded. |
| Structural steel — Level 3 to roof HPM-26 · 05-120 | Oct 12 – Oct 23 | Approved for work | medium 35 | Ironclad Steel Erectors Raising Gang A at reduced capacity Oct 22 – Oct 23. |
| Level 1 underground plumbing & rough-in HPM-26 · 22-300 | Oct 13 – Oct 21 | Approved for work | medium 35 | Level 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap. |
| Level 1 electrical rough-in HPM-26 · 26-310 | Oct 20 – Oct 27 | Approved for work | medium 35 | Brightline Electric Crew A assigned to two packages Oct 22 – Oct 23. |
| Fire sprinkler mains — Level 1 HPM-26 · 21-330 | Oct 20 – Oct 23 | Approved for work | medium 35 | Level 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap. |
| Level 2 framing & MEP rough-in HPM-26 · 09-600 | Nov 2 – Nov 20 | Verification outstanding | medium 30 | 1 required item(s) still to verify (next due Oct 30). |
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.