CrewCanvas
Dana Ruiz
superintendent

HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen

HPM-26 · Daily coordination report

Monday, October 19, 2026

Harbor Point Medical Pavilion · Prepared for the 6:30 AM foreman huddle

Superintendent summary

Blockers (1)

  • Level 2 slab-on-deck pour: 1 unverified required item
    Level 2 slab-on-deck pour is scheduled Oct 22 – Oct 23 but these required checklist items are not verified: “Special inspection of L2 steel connections (bolting & welds) — report received” (pending, Keystone Testing & Inspection).

Today's active work

PackageCrewProgressReadiness
Structural steel — Level 3 to roofIronclad Steel Erectors · Raising Gang A45%Approved for work
Level 1 underground plumbing & rough-inDelta Mechanical & Plumbing · Plumbing Crew 170%Approved for work

Starting in the next 5 days

PackageWindowVerifiedReadiness
Level 1 electrical rough-inOct 20 – Oct 273/3Approved for work
Fire sprinkler mains — Level 1Oct 20 – Oct 232/2Approved for work
Level 2 slab-on-deck pourOct 22 – Oct 235/6Blocked
Temporary power — Levels 2–3Oct 22 – Oct 232/2Awaiting approval

Schedule conflicts (6)

  • highLevel 1 East: “Level 1 underground plumbing & rough-in” and “Fire sprinkler mains — Level 1” overlap
  • highBrightline Electric Crew A assigned to two packages Oct 22 – Oct 23
  • highClearview Glazing Install Crew unavailable Oct 26 – Oct 27
  • high“Structural steel — Level 3 to roof” trending late — “Curtain wall — north & east elevations” at risk by 4d
  • mediumIronclad Steel Erectors Raising Gang A at reduced capacity Oct 22 – Oct 23
  • medium“Structural steel — Level 3 to roof” trending late — “Roofing — insulation & membrane” at risk by 2d

Actions for today

  1. Hold “Level 2 slab-on-deck pour” (Oct 22 – Oct 23). Do not release Summit Concrete Co. Placement Crew 1 or the 42m concrete pump until the outstanding item is verified. — Dana Ruiz (Superintendent)
  2. Get “Special inspection of L2 steel connections (bolting & welds) — report received” from Keystone Testing & Inspection by Oct 21 and attach the report as evidence. — Marcus Chen (Project Manager)
  3. Review the 2 verified checklist items for “Temporary power — Levels 2–3” and record a readiness decision before Oct 22. — Dana Ruiz (Superintendent)
  4. If not verified by Oct 21, swap sequence: move “Loading dock slab-on-grade” to Oct 22 so Summit Concrete Co. Placement Crew 1 stays productive, and move “Level 2 slab-on-deck pour” to Oct 28. — Dana Ruiz (Superintendent)
  5. Start “Fire sprinkler mains — Level 1” in Level 1 East on Oct 22, after “Level 1 underground plumbing & rough-in” finishes — or agree a split work-area plan for Oct 20 – Oct 21 at the daily huddle. — Dana Ruiz (Superintendent)
  6. Ask Brightline Electric to staff “Temporary power — Levels 2–3” with Crew B (3 workers, Devon Pike) Oct 22 – Oct 23. — Marcus Chen (Project Manager)
  7. Confirm with Nate Kim (Clearview Glazing) whether “Curtain wall — north & east elevations” can start Oct 28; otherwise re-plan the first days. — Dana Ruiz (Superintendent)
  8. Ask Rae Donnelly (Ironclad Steel Erectors) for a recovery plan on “Structural steel — Level 3 to roof”, or move “Curtain wall — north & east elevations” to Oct 30. — Marcus Chen (Project Manager)

Readiness approvals needed

  • Loading dock slab-on-grade — starts Oct 28
  • Temporary power — Levels 2–3 — starts Oct 22

Evidence received (last 72 h)

  • Roof beams grid A — crane pick · Dana Ruiz, Oct 17, 1:10 PM
  • L2 leading-edge protection — north bay · Owen Hale, Oct 17, 10:25 AM
  • Plumbing L1 East status · Dana Ruiz, Oct 16, 4:50 PM
  • Steel L3–Roof daily progress · Dana Ruiz, Oct 16, 4:45 PM
  • Special inspection follow-up · Marcus Chen, Oct 16, 3:30 PM
  • MEP embed sign-off sheet — Level 2 · Priya Natarajan, Oct 16, 3:00 PM
  • L2 deck side-lap fasteners — grid C/4 · Priya Natarajan, Oct 16, 2:05 PM
Readiness states reflect verified checklist records and recorded approvals only. Generated summaries are advisory and do not authorize work.