HPM-26 · Harbor Point Health Partners
Harbor Point Medical Pavilion
Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf
Superintendent Dana Ruiz
Project manager Marcus Chen
Ironclad Steel Erectors
Structural steel
Assignments
- Structural steel — Levels 1–2Sep 28 – Oct 9Complete
- Structural steel — Level 3 to roofOct 12 – Oct 23Approved for work
Owes verification
- Roof deck accepted from steel erector — due Oct 27
Summit Concrete Co.
Concrete
Assignments
- Foundations & footingsSep 8 – Sep 25Complete
- Level 2 slab-on-deck pourOct 22 – Oct 23Blocked
- Loading dock slab-on-gradeOct 28 – Oct 29Awaiting approval
Brightline Electric
Electrical
Assignments
- Level 1 electrical rough-inOct 20 – Oct 27Approved for work
- Temporary power — Levels 2–3Oct 22 – Oct 23Awaiting approval
Delta Mechanical & Plumbing
Plumbing / HVAC
Assignments
- Level 1 underground plumbing & rough-inOct 13 – Oct 21Approved for work
- Level 2 framing & MEP rough-inNov 2 – Nov 20Verification outstanding
Apex Fire Protection
Fire sprinkler
Assignments
- Fire sprinkler mains — Level 1Oct 20 – Oct 23Approved for work
Clearview Glazing
Curtain wall / glazing
Assignments
- Curtain wall — north & east elevationsOct 26 – Nov 13Verification outstanding
Owes verification
- Glass delivery confirmed — due Oct 23
Ridgeline Roofing
Roofing
Assignments
- Roofing — insulation & membraneOct 29 – Nov 10Verification outstanding
Keystone Testing & Inspection
Special inspection (3rd party)
Owes verification
- Special inspection of L2 steel connections (bolting & welds) — report received — due Oct 21
- L2 slab cure & strength test (7-day) — due Oct 30