HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen

Ironclad Steel Erectors

Structural steel

Rae Donnelly · rae@ironclad.example
(253) 555-0141
Raising Gang A (6)
Assignments
  • Structural steel — Levels 1–2Sep 28 – Oct 9Complete
  • Structural steel — Level 3 to roofOct 12 – Oct 23Approved for work
Owes verification
  • Roof deck accepted from steel erector — due Oct 27

Summit Concrete Co.

Concrete

(253) 555-0177
Placement Crew 1 (8) · Site Crew 2 (5)
Assignments
  • Foundations & footingsSep 8 – Sep 25Complete
  • Level 2 slab-on-deck pourOct 22 – Oct 23Blocked
  • Loading dock slab-on-gradeOct 28 – Oct 29Awaiting approval

Brightline Electric

Electrical

(253) 555-0102
Crew A (4) · Crew B (3)
Assignments
  • Level 1 electrical rough-inOct 20 – Oct 27Approved for work
  • Temporary power — Levels 2–3Oct 22 – Oct 23Awaiting approval

Delta Mechanical & Plumbing

Plumbing / HVAC

Sam Okafor · sam@deltamech.example
(253) 555-0190
Plumbing Crew 1 (4) · Plumbing Crew 2 (3)
Assignments
  • Level 1 underground plumbing & rough-inOct 13 – Oct 21Approved for work
  • Level 2 framing & MEP rough-inNov 2 – Nov 20Verification outstanding

Apex Fire Protection

Fire sprinkler

Bea Lindqvist · bea@apexfire.example
(253) 555-0133
Sprinkler Crew (3)
Assignments
  • Fire sprinkler mains — Level 1Oct 20 – Oct 23Approved for work

Clearview Glazing

Curtain wall / glazing

(253) 555-0168
Install Crew (5)
Assignments
  • Curtain wall — north & east elevationsOct 26 – Nov 13Verification outstanding
Owes verification
  • Glass delivery confirmed — due Oct 23

Ridgeline Roofing

Roofing

Ana Petrov · ana@ridgeline.example
(253) 555-0115
Roofing Crew (6)
Assignments
  • Roofing — insulation & membraneOct 29 – Nov 10Verification outstanding

Keystone Testing & Inspection

Special inspection (3rd party)

(253) 555-0109
Inspection agency — no crews
Owes verification
  • Special inspection of L2 steel connections (bolting & welds) — report received — due Oct 21
  • L2 slab cure & strength test (7-day) — due Oct 30