HPM-26 · Harbor Point Health Partners
Harbor Point Medical Pavilion
Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf
Site readiness checklists
Record verification results, then an authorized superintendent or PM records the readiness decision.
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.
03-200 · Oct 22–Oct 23 · Summit Concrete Co. · Placement Crew 1
Level 2 slab-on-deck pour
5 of 6 required items verified · starts in 3 days
- pendingprerequisiteBlocking
Special inspection of L2 steel connections (bolting & welds) — report received
Keystone Testing & Inspection · due Oct 21
Inspection requested Oct 15. Keystone has not issued the field report.
- verifiedquality
Metal deck attachment & side-lap fasteners inspected
Northline project engineer · verified by Priya Natarajan, Oct 16, 2:10 PM · 1 evidence
- verifiedprerequisite
Embeds, sleeves & deck penetrations signed off by MEP trades
Delta / Brightline / Apex · verified by Priya Natarajan, Oct 16, 3:00 PM · 1 evidence
- verifiedquality
Welded wire reinforcement placement inspected
Keystone Testing & Inspection · verified by Priya Natarajan, Oct 17, 12:00 PM
- verifiedlogistics
Mix design, pump & truck schedule confirmed with supplier
Summit Concrete Co. · verified by Luis Ortega, Oct 16, 9:00 AM
- verifiedsafety
Leading-edge & perimeter fall protection in place on L2
Northline safety · verified by Owen Hale, Oct 17, 10:30 AM · 1 evidence
- verifiedlogistics · optional
Pour-day weather forecast reviewed
Northline superintendent · verified by Dana Ruiz, Oct 18, 8:00 AM
Dry through Oct 23 (10% precip).
26-320 · Oct 22–Oct 23 · Brightline Electric · Crew A
Temporary power — Levels 2–3
2 of 2 required items verified · starts in 3 days
- verifiedpermit
Temporary power plan approved
Brightline Electric · verified by Priya Natarajan, Oct 15, 11:00 AM
- verifiedsafety
Lockout/tagout briefing completed
Brightline Electric · verified by Owen Hale, Oct 16, 8:00 AM
03-210 · Oct 28–Oct 29 · Summit Concrete Co. · Placement Crew 1
Loading dock slab-on-grade
3 of 3 required items verified · starts in 9 days
- verifiedprerequisite
Subgrade compaction test passed
Keystone Testing & Inspection · verified by Priya Natarajan, Oct 14, 1:00 PM · 1 evidence
- verifiedquality
Under-slab vapor barrier & dowels inspected
Northline project engineer · verified by Priya Natarajan, Oct 15, 1:00 PM
- verifiedlogistics
Truck access route & washout location set
Summit Concrete Co. · verified by Luis Ortega, Oct 15, 2:00 PM
08-400 · Oct 26–Nov 13 · Clearview Glazing · Install Crew
Curtain wall — north & east elevations
1 of 3 required items verified · starts in 7 days
- verifiedprerequisite
Curtain wall shop drawings approved
Clearview Glazing · verified by Priya Natarajan, Oct 2, 11:00 AM
- pendingprerequisite
Embed plates surveyed — north & east
Northline survey · due Oct 24
- pendinglogistics
Glass delivery confirmed
Clearview Glazing · due Oct 23
07-500 · Oct 29–Nov 10 · Ridgeline Roofing · Roofing Crew
Roofing — insulation & membrane
1 of 2 required items verified · starts in 10 days
- pendingprerequisite
Roof deck accepted from steel erector
Ironclad Steel Erectors · due Oct 27
- verifiedsafety
Material hoisting pick plan
Ridgeline Roofing · verified by Owen Hale, Oct 16, 12:00 PM
09-600 · Nov 2–Nov 20 · Delta Mechanical & Plumbing · Plumbing Crew 1
Level 2 framing & MEP rough-in
0 of 1 required items verified · starts in 14 days
- pendingprerequisite
L2 slab cure & strength test (7-day)
Keystone Testing & Inspection · due Oct 30
05-120 · Oct 12–Oct 23 · Ironclad Steel Erectors · Raising Gang A
Structural steel — Level 3 to roof
2 of 2 required items verified · active
- verifiedsafety
Crane lift plan updated for upper levels
Ironclad Steel Erectors · verified by Owen Hale, Oct 9, 11:00 AM
- verifiedsafety
Perimeter cable & fall-protection anchors installed L3
Ironclad Steel Erectors · verified by Owen Hale, Oct 9, 11:30 AM · 1 evidence
22-300 · Oct 13–Oct 21 · Delta Mechanical & Plumbing · Plumbing Crew 1
Level 1 underground plumbing & rough-in
1 of 1 required items verified · active
- verifiedpermit
Underground plumbing permit inspection scheduled
Delta Mechanical & Plumbing · verified by Priya Natarajan, Oct 12, 10:00 AM
26-310 · Oct 20–Oct 27 · Brightline Electric · Crew A
Level 1 electrical rough-in
3 of 3 required items verified · starts in 1 day
- verifiedprerequisite
Level 1 West turned over by plumbing
Delta Mechanical & Plumbing · verified by Dana Ruiz, Oct 16, 4:00 PM
- verifiedquality
Electrical drawings Rev C on site
Brightline Electric · verified by Priya Natarajan, Oct 16, 4:10 PM
- verifiedsafety
Scissor lift annual inspection current
Brightline Electric · verified by Owen Hale, Oct 17, 9:00 AM
21-330 · Oct 20–Oct 23 · Apex Fire Protection · Sprinkler Crew
Fire sprinkler mains — Level 1
2 of 2 required items verified · starts in 1 day
- verifiedpermit
Hydraulic calcs approved by fire marshal
Apex Fire Protection · verified by Priya Natarajan, Oct 10, 11:00 AM
- verifiedprerequisite
Hanger layout clash-checked against plumbing
Apex Fire Protection · verified by Priya Natarajan, Oct 15, 11:00 AM
- not applicablesafety · optional
Hot work permit
Apex Fire Protection
Grooved / threaded pipe — no hot work.