HPM-26 · Harbor Point Health Partners

Harbor Point Medical Pavilion

Bayview, WA · Healthcare · 4-story steel frame · 62,000 sf

Superintendent Dana Ruiz
Project manager Marcus Chen

Site readiness checklists

Record verification results, then an authorized superintendent or PM records the readiness decision.

Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.

03-200 · Oct 22–Oct 23 · Summit Concrete Co. · Placement Crew 1

Level 2 slab-on-deck pour

5 of 6 required items verified · starts in 3 days

Blocked
  • pendingprerequisiteBlocking

    Special inspection of L2 steel connections (bolting & welds) — report received

    Keystone Testing & Inspection · due Oct 21

    Inspection requested Oct 15. Keystone has not issued the field report.

  • verifiedquality

    Metal deck attachment & side-lap fasteners inspected

    Northline project engineer · verified by Priya Natarajan, Oct 16, 2:10 PM · 1 evidence

  • verifiedprerequisite

    Embeds, sleeves & deck penetrations signed off by MEP trades

    Delta / Brightline / Apex · verified by Priya Natarajan, Oct 16, 3:00 PM · 1 evidence

  • verifiedquality

    Welded wire reinforcement placement inspected

    Keystone Testing & Inspection · verified by Priya Natarajan, Oct 17, 12:00 PM

  • verifiedlogistics

    Mix design, pump & truck schedule confirmed with supplier

    Summit Concrete Co. · verified by Luis Ortega, Oct 16, 9:00 AM

  • verifiedsafety

    Leading-edge & perimeter fall protection in place on L2

    Northline safety · verified by Owen Hale, Oct 17, 10:30 AM · 1 evidence

  • verifiedlogistics · optional

    Pour-day weather forecast reviewed

    Northline superintendent · verified by Dana Ruiz, Oct 18, 8:00 AM

    Dry through Oct 23 (10% precip).

Approval unavailable: 1 required item not verified.

26-320 · Oct 22–Oct 23 · Brightline Electric · Crew A

Temporary power — Levels 2–3

2 of 2 required items verified · starts in 3 days

Checklist verified · awaiting approval
  • verifiedpermit

    Temporary power plan approved

    Brightline Electric · verified by Priya Natarajan, Oct 15, 11:00 AM

  • verifiedsafety

    Lockout/tagout briefing completed

    Brightline Electric · verified by Owen Hale, Oct 16, 8:00 AM

You are approving as Dana Ruiz. This records your decision against the 2 verified items above.

03-210 · Oct 28–Oct 29 · Summit Concrete Co. · Placement Crew 1

Loading dock slab-on-grade

3 of 3 required items verified · starts in 9 days

Checklist verified · awaiting approval
  • verifiedprerequisite

    Subgrade compaction test passed

    Keystone Testing & Inspection · verified by Priya Natarajan, Oct 14, 1:00 PM · 1 evidence

  • verifiedquality

    Under-slab vapor barrier & dowels inspected

    Northline project engineer · verified by Priya Natarajan, Oct 15, 1:00 PM

  • verifiedlogistics

    Truck access route & washout location set

    Summit Concrete Co. · verified by Luis Ortega, Oct 15, 2:00 PM

You are approving as Dana Ruiz. This records your decision against the 3 verified items above.

08-400 · Oct 26–Nov 13 · Clearview Glazing · Install Crew

Curtain wall — north & east elevations

1 of 3 required items verified · starts in 7 days

Verification outstanding
  • verifiedprerequisite

    Curtain wall shop drawings approved

    Clearview Glazing · verified by Priya Natarajan, Oct 2, 11:00 AM

  • pendingprerequisite

    Embed plates surveyed — north & east

    Northline survey · due Oct 24

  • pendinglogistics

    Glass delivery confirmed

    Clearview Glazing · due Oct 23

Approval unavailable: 2 required items not verified.

07-500 · Oct 29–Nov 10 · Ridgeline Roofing · Roofing Crew

Roofing — insulation & membrane

1 of 2 required items verified · starts in 10 days

Verification outstanding
  • pendingprerequisite

    Roof deck accepted from steel erector

    Ironclad Steel Erectors · due Oct 27

  • verifiedsafety

    Material hoisting pick plan

    Ridgeline Roofing · verified by Owen Hale, Oct 16, 12:00 PM

Approval unavailable: 1 required item not verified.

09-600 · Nov 2–Nov 20 · Delta Mechanical & Plumbing · Plumbing Crew 1

Level 2 framing & MEP rough-in

0 of 1 required items verified · starts in 14 days

Verification outstanding
  • pendingprerequisite

    L2 slab cure & strength test (7-day)

    Keystone Testing & Inspection · due Oct 30

Approval unavailable: 1 required item not verified.

05-120 · Oct 12–Oct 23 · Ironclad Steel Erectors · Raising Gang A

Structural steel — Level 3 to roof

2 of 2 required items verified · active

Approved for work
  • verifiedsafety

    Crane lift plan updated for upper levels

    Ironclad Steel Erectors · verified by Owen Hale, Oct 9, 11:00 AM

  • verifiedsafety

    Perimeter cable & fall-protection anchors installed L3

    Ironclad Steel Erectors · verified by Owen Hale, Oct 9, 11:30 AM · 1 evidence

Approved for work by Dana Ruiz · Oct 10, 8:00 AM — “Released for erection L3–Roof.”

22-300 · Oct 13–Oct 21 · Delta Mechanical & Plumbing · Plumbing Crew 1

Level 1 underground plumbing & rough-in

1 of 1 required items verified · active

Approved for work
  • verifiedpermit

    Underground plumbing permit inspection scheduled

    Delta Mechanical & Plumbing · verified by Priya Natarajan, Oct 12, 10:00 AM

Approved for work by Dana Ruiz · Oct 12, 8:30 AM

26-310 · Oct 20–Oct 27 · Brightline Electric · Crew A

Level 1 electrical rough-in

3 of 3 required items verified · starts in 1 day

Approved for work
  • verifiedprerequisite

    Level 1 West turned over by plumbing

    Delta Mechanical & Plumbing · verified by Dana Ruiz, Oct 16, 4:00 PM

  • verifiedquality

    Electrical drawings Rev C on site

    Brightline Electric · verified by Priya Natarajan, Oct 16, 4:10 PM

  • verifiedsafety

    Scissor lift annual inspection current

    Brightline Electric · verified by Owen Hale, Oct 17, 9:00 AM

Approved for work by Dana Ruiz · Oct 17, 4:30 PM

21-330 · Oct 20–Oct 23 · Apex Fire Protection · Sprinkler Crew

Fire sprinkler mains — Level 1

2 of 2 required items verified · starts in 1 day

Approved for work
  • verifiedpermit

    Hydraulic calcs approved by fire marshal

    Apex Fire Protection · verified by Priya Natarajan, Oct 10, 11:00 AM

  • verifiedprerequisite

    Hanger layout clash-checked against plumbing

    Apex Fire Protection · verified by Priya Natarajan, Oct 15, 11:00 AM

  • not applicablesafety · optional

    Hot work permit

    Apex Fire Protection

    Grooved / threaded pipe — no hot work.

Approved for work by Dana Ruiz · Oct 16, 4:40 PM