NLC-26 · Northgate Industrial REIT
Northgate Logistics Center — Tenant Fit-out
Kent Valley, WA · Industrial · Interior fit-out · 18,500 sf office
Superintendent Jo Whitaker
Project manager Marcus Chen
Work packages
3 packages · scope, assignments and readiness
- Approved for work
Office restroom plumbing
22-010 · Plumbing
- Window
- Oct 14 – Oct 23
- Zone
- Office core
- Crew
- Delta Mechanical & Plumbing · Plumbing Crew 2
60% - Verification outstanding
Office electrical rough-in
26-020 · Electrical
- Window
- Oct 26 – Oct 30
- Zone
- Office area
- Crew
- Brightline Electric · Crew B
- Depends on
- Office restroom plumbing (FS)
0% - Verification outstanding
Sprinkler drops & heads — office
21-030 · Fire sprinkler
- Window
- Nov 2 – Nov 6
- Zone
- Office area
- Crew
- Apex Fire Protection · Sprinkler Crew
- Depends on
- Office electrical rough-in (FS)
0%
| Package | Zone | Subcontractor · crew | Window | Progress | Depends on | Readiness |
|---|---|---|---|---|---|---|
Office restroom plumbing 22-010 · Plumbing | Office core | Delta Mechanical & Plumbing Plumbing Crew 2 | Oct 14 – Oct 23 | 60% plan 50% | — | Approved for work |
Office electrical rough-in 26-020 · Electrical | Office area | Brightline Electric Crew B | Oct 26 – Oct 30 | 0% | 22-010 FS · earliest Oct 24 | Verification outstanding |
Sprinkler drops & heads — office 21-030 · Fire sprinkler | Office area | Apex Fire Protection Sprinkler Crew | Nov 2 – Nov 6 | 0% | 26-020 FS · earliest Oct 31 | Verification outstanding |
Dependency network
Finish-to-start links with lag and rationale
- Office restroom plumbingFS →Office electrical rough-in
- Office electrical rough-inFS →Sprinkler drops & heads — office