CrewCanvas
Dana Ruiz
superintendent

NLC-26 · Northgate Industrial REIT

Northgate Logistics Center — Tenant Fit-out

Kent Valley, WA · Industrial · Interior fit-out · 18,500 sf office

Superintendent Jo Whitaker
Project manager Marcus Chen

Work packages

3 packages · scope, assignments and readiness

  • Office restroom plumbing

    22-010 · Plumbing

    Approved for work
    Window
    Oct 14 – Oct 23
    Zone
    Office core
    Crew
    Delta Mechanical & Plumbing · Plumbing Crew 2
    60%
  • Office electrical rough-in

    26-020 · Electrical

    Verification outstanding
    Window
    Oct 26 – Oct 30
    Zone
    Office area
    Crew
    Brightline Electric · Crew B
    Depends on
    Office restroom plumbing (FS)
    0%
  • Sprinkler drops & heads — office

    21-030 · Fire sprinkler

    Verification outstanding
    Window
    Nov 2 – Nov 6
    Zone
    Office area
    Crew
    Apex Fire Protection · Sprinkler Crew
    Depends on
    Office electrical rough-in (FS)
    0%

Dependency network

Finish-to-start links with lag and rationale

  • Office restroom plumbingFS →Office electrical rough-in
  • Office electrical rough-inFS →Sprinkler drops & heads — office