NLC-26 · Northgate Industrial REIT
Northgate Logistics Center — Tenant Fit-out
Kent Valley, WA · Industrial · Interior fit-out · 18,500 sf office
Site readiness checklists
Record verification results, then an authorized superintendent or PM records the readiness decision.
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.
26-020 · Oct 26–Oct 30 · Brightline Electric · Crew B
Office electrical rough-in
1 of 2 required items verified · starts in 7 days
- pendingprerequisite
Office walls framed & top track inspected
Northline · due Oct 23
- verifiedpermit
Electrical permit posted
Brightline Electric · verified by Jo Whitaker, Oct 15, 10:00 AM
21-030 · Nov 2–Nov 6 · Apex Fire Protection · Sprinkler Crew
Sprinkler drops & heads — office
0 of 1 required items verified · starts in 14 days
- pendingprerequisite
Ceiling grid layout approved
Northline · due Oct 30
22-010 · Oct 14–Oct 23 · Delta Mechanical & Plumbing · Plumbing Crew 2
Office restroom plumbing
1 of 1 required items verified · active
- verifiedpermit
Rough plumbing permit
Delta Mechanical & Plumbing · verified by Jo Whitaker, Oct 13, 10:00 AM