NLC-26 · Northgate Industrial REIT

Northgate Logistics Center — Tenant Fit-out

Kent Valley, WA · Industrial · Interior fit-out · 18,500 sf office

Superintendent Jo Whitaker
Project manager Marcus Chen

Site readiness checklists

Record verification results, then an authorized superintendent or PM records the readiness decision.

Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.

26-020 · Oct 26–Oct 30 · Brightline Electric · Crew B

Office electrical rough-in

1 of 2 required items verified · starts in 7 days

Verification outstanding
  • pendingprerequisite

    Office walls framed & top track inspected

    Northline · due Oct 23

  • verifiedpermit

    Electrical permit posted

    Brightline Electric · verified by Jo Whitaker, Oct 15, 10:00 AM

Approval unavailable: 1 required item not verified.

21-030 · Nov 2–Nov 6 · Apex Fire Protection · Sprinkler Crew

Sprinkler drops & heads — office

0 of 1 required items verified · starts in 14 days

Verification outstanding
  • pendingprerequisite

    Ceiling grid layout approved

    Northline · due Oct 30

Approval unavailable: 1 required item not verified.

22-010 · Oct 14–Oct 23 · Delta Mechanical & Plumbing · Plumbing Crew 2

Office restroom plumbing

1 of 1 required items verified · active

Approved for work
  • verifiedpermit

    Rough plumbing permit

    Delta Mechanical & Plumbing · verified by Jo Whitaker, Oct 13, 10:00 AM

Approved for work by Jo Whitaker · Oct 13, 11:00 AM