NLC-26 · Northgate Industrial REIT
Northgate Logistics Center — Tenant Fit-out
Kent Valley, WA · Industrial · Interior fit-out · 18,500 sf office
Blockers
Required checklist items not verified before scheduled work
Schedule conflicts
Crews, work windows, equipment and dependencies
Readiness risk ranking
Additive score — every point is explained below. Critical ≥ 70 · High ≥ 45 · Medium ≥ 20
- 01
Office electrical rough-in
Oct 26 – Oct 30 · Office area
Verification outstandingmedium23Why this warning- 1 required item(s) still to verify (next due Oct 23).
- Starts in 7 days.
Recommended actions- verify
Close out 1 open item(s) for “Office electrical rough-in”: “Office walls framed & top track inspected” (Northline, due Oct 23).
Owner: Marcus Chen (Project Manager) · Office electrical rough-in · P3
Open checklist →They become blockers 3 days before the Oct 26 start.
AIDeterministic summary (Bedrock off) - 02
Sprinkler drops & heads — office
Nov 2 – Nov 6 · Office area
Verification outstandinglow15Why this warning- 1 required item(s) still to verify (next due Oct 30).
- 03
Office restroom plumbing
Oct 14 – Oct 23 · Office core
Approved for worklow0Why this warning
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.