CRT-27 · Cedar Row Living LLC
Cedar Row Townhomes — Phase 2
Maple Hollow, WA · Multifamily · 24 wood-frame units
Superintendent Jo Whitaker
Project manager Marcus Chen
Work packages
2 packages · scope, assignments and readiness
- Verification outstanding
Site utilities — sanitary & storm
33-010 · Civil / concrete
- Window
- Nov 2 – Nov 20
- Zone
- Site
- Crew
- Summit Concrete Co. · Site Crew 2
0% - Awaiting approval
Building A foundations
03-020 · Concrete
- Window
- Nov 23 – Dec 11
- Zone
- Building A
- Crew
- Summit Concrete Co. · Site Crew 2
- Depends on
- Site utilities — sanitary & storm (FS)
0%
| Package | Zone | Subcontractor · crew | Window | Progress | Depends on | Readiness |
|---|---|---|---|---|---|---|
Site utilities — sanitary & storm 33-010 · Civil / concrete · Excavator | Site | Summit Concrete Co. Site Crew 2 | Nov 2 – Nov 20 | 0% | — | Verification outstanding |
Building A foundations 03-020 · Concrete | Building A | Summit Concrete Co. Site Crew 2 | Nov 23 – Dec 11 | 0% | 33-010 FS · earliest Nov 21 | Awaiting approval |
Dependency network
Finish-to-start links with lag and rationale
- Site utilities — sanitary & stormFS →Building A foundations