CrewCanvas
Dana Ruiz
superintendent

CRT-27 · Cedar Row Living LLC

Cedar Row Townhomes — Phase 2

Maple Hollow, WA · Multifamily · 24 wood-frame units

Superintendent Jo Whitaker
Project manager Marcus Chen

Blockers

Required checklist items not verified before scheduled work

No schedule conflicts in the look-ahead window.

Schedule conflicts

Crews, work windows, equipment and dependencies

No schedule conflicts in the look-ahead window.

Readiness risk ranking

Additive score — every point is explained below. Critical ≥ 70 · High ≥ 45 · Medium ≥ 20

  1. 01

    Site utilities — sanitary & storm

    Nov 2 – Nov 20 · Site

    Verification outstandinglow15
    Why this warning
    • 2 required item(s) still to verify (next due Oct 28).
    Recommended actions

    No action suggested.

    Open checklist →

Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.