CRT-27 · Cedar Row Living LLC
Cedar Row Townhomes — Phase 2
Maple Hollow, WA · Multifamily · 24 wood-frame units
Superintendent Jo Whitaker
Project manager Marcus Chen
Site readiness checklists
Record verification results, then an authorized superintendent or PM records the readiness decision.
Readiness comes only from verified checklist records and an authorized person's approval. AI text summarizes those records and suggests actions; it never marks work safe or ready.
03-020 · Nov 23–Dec 11 · Summit Concrete Co. · Site Crew 2
Building A foundations
0 of 0 required items verified · starts in 35 days
33-010 · Nov 2–Nov 20 · Summit Concrete Co. · Site Crew 2
Site utilities — sanitary & storm
0 of 2 required items verified · starts in 14 days
- pendingpermit
Grading permit issued
Cedar Row Living LLC · due Oct 28
- pendingsafety
Utility locate ticket active
Summit Concrete Co. · due Oct 29